The Ekam Settlement Additional Drainage Works project is a collaborative effort between the Government of Haiti and the United States Agency for International Development (USAID). The project aims to improve drainage and reduce flood risk in the Ekam Settlement area. The project scope includes the construction of a swale, a type of shallow ditch or depression that collects and redirects water.
The swale’s centerline is aligned with a specific gradient, as indicated in the Alignment – Swale Centerline drawing. The centerline’s reference points are listed in a series of coordinates, including -0+10, 0+00, 1+00, and 2+00, among others. These coordinates are used to establish the swale’s alignment and ensure proper drainage.
The project’s civil engineering design involves the construction of a swale with a specific cross-sectional profile. The swale’s dimensions and geometry are critical to its effectiveness in managing water flow and reducing flood risk. The project’s engineers have carefully planned the swale’s layout to ensure optimal drainage and minimize the risk of erosion.
The project’s implementation is expected to have a significant impact on the Ekam Settlement area. By improving drainage and reducing flood risk, the project will help to protect homes, businesses, and infrastructure from damage. The project’s success will also contribute to the overall development of the Ekam Settlement area, improving the quality of life for residents and supporting economic growth.
The project’s timeline is critical to its success. The project was initially revised on 12 January 2018, with further revisions made on 10 April 2018. The project’s index of drawings provides a comprehensive overview of the project’s design and engineering plans, including the Swale Centerline A-A drawing and the Alignment – Swale Centerline drawing.